PPFSWG 2016 Draft Work Plan
Draft: Port Performance Freight Statistics Working Group 2016 Work Plan
BACKGROUND
The Port Performance Freight Statistics Working Group (hereafter, Working Group) has been created in accordance with Section 6018 of the Fixing America’s Surface Transportation (FAST) Act (P.L. 114-94; Dec. 4, 2015; 129 Stat. 1312). The Working Group supports development of the newly-established Bureau of Transportation Statistics (BTS) Port Performance Freight Statistics Program. The goal of the program is “tprovide nationally consistent measures of performance” of the nation’s largest ports and treport annually tCongress on port capacity and throughput. The FAST Act requires the Director of BTS tcommission a Working Group tprovide recommendations tBTS on matters related tport performance measures and identifies the membership of this group.
WORKING GROUP ACTIVITIES AND DELIVERABLES: JULY 2016-DECEMBER 2016
- Provide short- and long-term recommendations tDirector of BTS
The FAST Act requires the Working Group tprovide recommendations tthe BTS Director on:- Short-term: Nationally-consistent port performance measures on port capacity and throughput, including specifications and data measurements tbe used in the newly-established Port Performance Freight Statistics Program; and
- Long-term: A process for the U.S. Department of Transportation tcollect timely and nationally consistent data.
The FAST Act sets a due date for recommendations tthe BTS Director of December 4, 2016.
Deliverables:
- Member approved Working Group bylaws
- Working Group work plan
- Chair/Vice Chair approved meeting minutes for each meeting of the Working Group
- Working Group recommendation on port definitions
- Working Group recommendations on port performance capacity and throughput measures
- Working Group recommendations on BTS data collection process
WORKING GROUP KEY DATES AND MILESTONES: JULY 2016-DECEMBER 2016
The table below provides a high-level view of key dates and milestones for Working Group meetings and anticipated activities from June 2016 through January 2017. Additional detail on these meetings is provided on page 3 of this document.
Date | Key Milestones |
---|---|
15-Jul-16 | 1st Working Group Meeting |
1-Aug-16 | Deadline for members to submit preliminary individual responses tthe three questions as interim work product (for three questions, see Table below) |
9-Sep-16 | Working Group develops Draft Work Plan |
23-Sep-16 |
2nd Working Group Meeting
|
3-Oct-16 | Working Group publishes Work Plan for public comment |
7-Oct-16 | Working Group provides initial recommendation on port capacity and throughput measures |
21-Oct-16 |
3rd Working Group Meeting
|
18-Nov-16 |
4th Working Group Meeting
|
4-Dec-16 | Working Group submits final recommendations tBTS Director |
WORKING GROUP PROPOSED MEETING SCHEDULE, AGENDA ITEMS, AND ANTICIPATED ACTIONS
In 2016, the Working Group will hold four meetings. The table below summarizes the schedule, agenda items, and anticipated follow-up actions for each of these meetings.
Meeting Date | Agenda Items | Anticipated Follow-Up Actions |
---|---|---|
July 15, 2016 (meeting complete) 1-day meeting Place: U.S. Department of Transportation, Washington, DC |
|
|
September 23, 2016 1-day meeting Place: U.S. Department of Transportation, Washington, DC |
|
|
October 21, 2016 1-day meeting Place: U.S. Department of Transportation, Washington, DC |
|
|
November 18, 2016 1-day meeting Place: U.S. Department of Transportation, Washington, DC |
|
|